PRESS RELEASE
07 October 2026
Ombudsman vows protection of IP rights in gov’t dredging projects
QUEZON CITY, Philippines—The Office of the Ombudsman vowed to protect indigenous peoples’ (IP) rights against illegal, unjust, improper, or inefficient acts in the implementation of government projects affecting their communities.
Ombudsman Jesus Crispin Remulla on Wednesday cited a recent decision of the agency involving the rehabilitation and dredging of the Malinao River in Brgy. Simpokan, Puerto Princesa City.
The case stemmed from a complaint by the President and Vice President of the Sambayaang Tagbanua kat Barangay Simpokan Inc. (STBSI) against Carlo Benitez Gomez, Department Head II of the City Environment and Natural Resources Office of the Puerto Princesa City Government. Also listed as respondents were the then Barangay Captain, seven barangay councilors, and the Sangguniang Kabataan Chairman.
Together with another complainant, the STBSI leaders stated that they were part owners of an ancestral domain belonging to the Tagbanua Indigenous Cultural Communities/Indigenous Peoples (ICCs/IPs) in Puerto Princesa City.
They averred that in 2022, the officials of Brgy. Simpokan passed a resolution for the rehabilitation of the said river without appropriate consultation with or consent from ICC/IP leaders.
The complaint stated that there was a “lack of proper consultation and permission from their indigenous leaders”, and that there was a “blatant desecration of their culture and traditions” for allowing the extraction of gravel deposits from the Malinao River.
According to the decision, Gomez, as technical secretariat of the City Mining Regulatory Board (CMRB), issued a clearance to proceed with the rehabilitation, allegedly to counter the effects of typhoon Odette.
One of the conditions of the clearance was that the rehabilitation contractor would receive 6,000 cubic meters of surplus gravel deposits taken from the Malinao River in exchange for the operational costs it would incur.
The STBSI expressed its outright opposition to the project, arguing that the project violated Section 59 of RA 8371 or the Indigenous Peoples’ Rights Act (IPRA) of 1997.
The Ombudsman ruled that Gomez was administratively liable for Conduct Unbecoming of a Public Officer.
The decision found that Gomez issued the clearance to rehabilitate before obtaining the required National Commission on Indigenous Peoples (NCIP) certification and the CMRB approval.
The other barangay officials were cleared, having only participated in the issuance of the barangay resolution regarding the overflowing of the Malinao River.
“Gomez’s act of issuing clearance to proceed without the required certification precondition from the NCIP and without waiting for the CMRB’s approval is a deliberate transgression of rules or procedures as provided under the IPRA,” the decision stated.
“Gomez failed to observe professionalism and justness and sincerity so as to discourage wrong perception of his role as a dispenser or peddler of undue patronage. Such conduct or behavior is considered unbecoming of a public officer,” it added.
Gomez was meted the penalty of suspension for one year without pay. The decision likewise stated that in the event that the penalty of suspension can no longer be enforced due to respondent Gomez’s separation from the service, the penalty shall be converted into a fine in an amount equivalent to six months of his salary.
Ombudsman Remulla said that the agency will continue to protect the rights of IPs and warned government officials to respect laws protecting IP rights. #